Pressure test and evacuation of field refrigerant piping
What is going on
Field piping must be pressure tested with inert gas and vacuum tested before charging.
Check in this order
- Pressure test the field piping with nitrogen to 500 psi.
- Remove the pressure source and hold the pressure for at least 1 hour. The gauge must show no drop; gauge resolution must not exceed 5% of test pressure.
- Evacuate the system. Once it reaches the required vacuum level, isolate the pump.
- Confirm the pressure does not rise above 1500 microns within 10 minutes.
- Use a vacuum of 500 microns or less, or the level required by local code if that is stricter.
- Test field joints indoors at 125% of maximum allowable pressure with sensitivity of 1/8 oz (5 g) per year; no leak allowed.
Applies to: Split systems, field-made piping
More mini-split guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Carrier D5FSOAH installation manual, p. 5. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.