Connect refrigerant pipes and insulate
What is going on
Connect the low-pressure line first, then the high-pressure line. Do not let any other gas or substance enter the unit.
Check in this order
- Connect the copper pipes to the indoor unit first, then to the outdoor unit.
- Apply a thin coat of refrigeration oil to the flared ends.
- Align the centre of the two pipes, then tighten the flare nut by hand.
- Hold the unit tubing nut with a spanner and tighten the flare nut with a torque wrench to the value in the torque table.
- Bend the tubing gently at the middle. Do not exceed 90° or bend it more than 3 times. Minimum bend radius is 3.9 in (100 mm).
- Wrap the power cable, signal cable and piping together with binding tape. Do not twist the signal cable with other wiring.
- Thread the piping through the wall and connect it to the outdoor unit.
- Insulate all piping, including the outdoor unit valves. Bare pipe can cause burns or frostbite.
- Fix the water receiver (from the accessories box) to the indoor unit with a screw.
- Open the outdoor stop valves to let refrigerant flow between units.
- Check for leaks after installation. If a leak is found, ventilate the area immediately and evacuate the system.
Applies to: Refrigerant connections, 6K-18K
More mini-split guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5FSOAH installation instructions, p. 20. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.