The app shows the recommended charge to add to meet the required charge. The calculated subcool is shown once the system stabilizes at full speed. Gauge readings can take up to 5 minutes to reach the app.

Check in this order

  1. Add the recommended charge shown in the app.
  2. Wait for the system to stabilize and run at full speed.
  3. Read the calculated subcool shown in the app.
  4. Allow up to 5 minutes delay between gauge reading and app verification.
  5. Stop the verification to generate a report.

Applies to: Inverter systems using Daikin One Touch

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Daikin One Touch Smart Thermostat Training Module TRC-10, p. 31. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.