Pressure test field refrigerant piping
What is going on
After field piping is complete, pressure test with inert gas, then vacuum test before charging.
Check in this order
- Pressure test the field piping with inert gas before vacuum and charging.
- Test the low side at the low side design pressure and the high side at the high side design pressure. If the sides cannot be isolated, test the whole system to the low side design pressure.
- After removing the pressure source, hold the test pressure for at least 1 hour with no drop on the gauge. Gauge resolution must not exceed 5% of the test pressure.
Applies to: Split system field piping
More heat pump guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5CURA installation manual, p. 4. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.