Keep low voltage wiring separated from power wiring to prevent interference.
Check in this order
- Apply the rated voltage of 208/230 V.
- Install a main switch and a slow blow fuse on each phase.
- Keep low voltage wiring (remote controller and between units) at least 2 in. (50 mm) from power wiring.
- Secure power wiring to the power terminal block as described in section 7-4.
- Secure transmission wiring as described in section 7-3.
- Use clamps such as insulation lock ties so wires do not touch piping.
- Shape wires so the control box cover is not deformed, then close the cover firmly.
Applies to: Field wiring at heat source and cascade units
More heat pump guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Daikin Mega-Q installation manual, p. 24. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.