Daikin · Heat pump troubleshooting

Opening and closing the stop valves

DX6VSDZ6VSDZ6VSA

What is going on

Stop valves ship closed. They must be opened before start-up. Inadequate torque can leak refrigerant. The 3.5-5.0 ton FIT and 3.0-4.0 ton Enhanced Capacity units use a back sealing type valve, so the back seal must be closed as in the opening procedure. Torque values are in the stop valve tables.

Likely causes

  • Stop valve left closed at start-up
  • Insufficient tightening torque causing leakage

Check in this order

  1. Remove the valve lid and turn the valve counterclockwise with a hex wrench to open.
  2. Turn until the shaft stops.
  3. Then turn until the designated torque is reached, as in the stop valve table.
  4. Refit the valve lid.
  5. To close, remove the valve lid and turn clockwise until the shaft stops.
  6. Then tighten to the designated torque, and refit the valve lid.
  7. On back-sealing valves, seal the back seal as in opening step 3.
  8. Make sure both liquid and gas stop valves are open before start-up.

Applies to: Liquid and gas stop valves on DX6VS / DZ6VS / DZ6VSA units

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Daikin DX6VS/DZ6VS installation manual (3P731493-1), p. 17. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.