Use only if the vacuum pump cannot reach 1/4 inch and the system has no liquid water.
Check in this order
- Attach gauges and evacuate the system to 28 inches of mercury. Run the pump 15 minutes more.
- Close the service valves and shut off the pump.
- Connect a nitrogen cylinder and regulator. Flow nitrogen until system pressure is 2 psig.
- Close the service valve and let the system stand for 1 hour.
- Repeat the evacuation and nitrogen steps as shown in Fig. 35.
- Confirm the system holds a deep vacuum to show it is tight and dry.
Applies to: Refrigerant lines and indoor coil
More heat pump guides
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: D5CURA installation manual, p. 30. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.