Crossover start-up checklist: voltage checks

D5CURA

What is going on

Record installation data and check supply and communication wiring at each point.

Check in this order

  1. Record site, contractor, job, distributor, unit model and serial numbers.
  2. Record wire size and type, and confirm no splices or wire nuts between outdoor and indoor units.
  3. Confirm wiring from the outdoor port to the correct indoor unit.
  4. At the outdoor disconnect, measure 1(L1) to GND, 2(L2) to GND and 1(L1) to 2(L2).
  5. At the outdoor terminal block, repeat 1(L1) to GND, 2(L2) to GND and 1(L1) to 2(L2).
  6. At the indoor unit, measure 1(L1) to GND, 2(L2) to GND, 1(L1) to 2(L2) and 2(L2) to 3(S).
  7. Record any notes on the checklist.

Applies to: Outdoor and indoor unit wiring

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: D5CURA installation manual, p. 32. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.