Daikin · Heat pump troubleshooting

Connecting inter-unit piping to heat source and cascade units

Mega-Q

What is going on

Connection layout depends on whether the piping exits from the front or the bottom.

Check in this order

  1. Use the on-site inter-unit piping accessory to connect the heat source unit to the cascade unit.
  2. Route piping so it does not touch other piping, the bottom frame, or the side plates.
  3. For front exit, drill a knockout hole at the piping outlet and pass the piping through it.
  4. For bottom exit, open a knockout hole in the bottom frame and route the piping under the bottom frame.
  5. Braze the attached and field piping joints as shown in Table 5.

Applies to: Heat source unit and cascade unit inter-unit piping

More heat pump guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Daikin Mega-Q installation manual, p. 19. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.