Installing the drain lines

WEC

What is going on

Route the drainwater and NDI freeze prevention lines with a proper air gap.

Check in this order

  1. Unroll and straighten the LLDPE 1/2in and 1/4in tubes, then cut to length.
  2. Connect 1/2in fittings to the drainwater outlet and attach the 1/2in tube.
  3. Connect the 1/4in tube to the NDI module freeze prevention water outlet.
  4. Keep height at or below 10 ft (3 m) and length at or below 197 in. (5 m).
  5. Leave a 1-1/2in (40 mm) air gap between the tube end and the drain. Do not put the tube end into the drain.
  6. Use an L-shaped pipe at the tube end to stop splashing.
  7. Do not cap or plug the drain lines.
  8. Make sure the drain has no backflow or backpressure.

Applies to: WEC600

More general guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Navien WEC service manual, p. 20-21. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.