Goodman · Furnace troubleshooting

Direct vent (dual pipe) routing and terminations

34.5 in Chassis ACVC96/AMVC96/GCVC96/GMVC96

What is going on

Direct vent uses separate combustion air intake and vent pipes, run horizontally through a side wall or vertically through the roof.

Check in this order

  1. Run the intake and vent pipes both horizontally or both vertically.
  2. Pipes run through an unused chimney must extend at least 12 in above the chimney top.
  3. Close the space between the pipes and chimney with weather tight, corrosion resistant flashing.
  4. Keep intake and vent terminations in the same atmospheric pressure zone.
  5. For an alternate horizontal termination, keep at least 12 in between intake and vent and keep 3 to 24 in between the pipes.
  6. Use 90 degree elbows for the alternate termination, as shown in the figures.
  7. Intake may be snorkeled to get 12 in minimum ground clearance.
  8. If the intake runs above a finished ceiling or where condensate drip is a problem, insulate it with 1/2 in thick closed cell foam (such as Armaflex or Insultube).

Applies to: Direct vent installations

More furnace guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Goodman GMVC96 service manual, p. 16-17. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.