Weil-McLain · Boiler troubleshooting
Water piping and recommended pipe sizing
What is going on
The boiler has 3 inch Class 150 flanged connections, so use reducers to adapt to the external piping. Use two wrenches when tightening water piping at the boiler, holding the internal piping so it does not turn. Size the pumps and piping for the required temperature rise using the head loss curve (Figure 9) and flow table (Figure 10). Size system piping per Figure 11. For glycol mixes the temperature rise will differ, but flow must stay within range. Flows outside the Figure 10 range need primary/secondary piping, a differential bypass valve in variable primary systems for high flow, or a flow switch set at minimum flow for low flow. Insufficient flow causes limit nuisance outages; excess flow can erode the heat exchanger.
Check in this order
- Fit reducers from the 3 inch Class 150 flanges to the external piping.
- Hold the boiler internal piping with one wrench while tightening with the other.
- Select pipe size and pump for the desired temperature rise, using Figure 10 and Figure 11.
- For flows outside the Figure 10 range, use primary/secondary piping or a bypass valve (high flow) or a flow switch at minimum flow (low flow) in a variable primary system.
- For glycol systems, confirm flow stays in range and get the temperature rise from the glycol supplier.
Applies to: All SVF 1500-3000 models
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 1500-3000 Series 1 boiler manual, p. 14-16. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.