What is going on

Install the controls per the control tapping table and Figure 4. On EG water boilers the low water cutoff is built into the control when using the 381-356-589 sensor. If the system must be ASME inspected and approved, an additional high temperature limit is required.

Check in this order

  1. Install controls as shown in the control tapping table and Figure 4, page 14.
  2. Confirm the 381-356-589 sensor is used if the integral low water cutoff is relied on.
  3. If ASME inspection and approval is required, buy and install an additional high temperature limit in the supply line above the boiler.

Applies to: EG water boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG/PEG Series 7 boiler manual, p. 27. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.