Vertical concentric termination: roof penetration
What is going on
Prepare the roof opening and thimble before running the termination through it. Follow local codes for isolating vent pipe through floors, ceilings and roofs.
Check in this order
- For a 3 in termination, cut a 5 in diameter hole to clear the 4-1/2 in outside diameter.
- For a 4 in termination, cut a 6-1/2 in diameter hole to clear the 6 in outside diameter.
- Insert a galvanized metal thimble in the vent pipe hole.
- Install flashing and sealing boots sized for the concentric termination outside diameter.
Applies to: 3 in and 4 in vertical concentric termination
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Ultra Series 4 boiler manual, p. 76. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.