Vent termination location clearances

ECO Tec Series 3

What is going on

Choose the vent termination location so the plume, condensate and intake are clear of people, openings and other equipment. These apply to vertical terminations too.

Likely causes

  • Vent plume and condensate can damage surfaces or freeze and form ice.
  • Plume below a window can block the view.
  • Wind eddies can recirculate flue gas into the intake.

Check in this order

  1. Keep at least 4 ft horizontally from electrical meters, gas meters, regulators and relief equipment, and never terminate above or below them unless that 4 ft horizontal distance is kept.
  2. Do not terminate above a door or window or above a public walkway.
  3. Keep the termination out of spaces where wind eddies can recirculate exhaust.
  4. Keep vent and air intake areas clear of accumulating snow.
  5. Check the clearance figure (Figure 32, page 30) for openable windows, doors, roof overhangs, decks, grade, and the air intake distances.
  6. Use the U.S. clearances in the figure; use CAN/CSA B149.1 for Canadian installations.

Applies to: ECO Tec Series 3 sidewall and vertical vent terminations

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec series 3 boiler manual, p. 30. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.