What is going on
The boiler is heavy and must not be dropped. Remove the shipping brackets from the pallet using the ramp, which needs room for the boiler length plus 76 inches at the piping end. Apply force only at jacket corner posts or water manifolds, never on the water or gas pipes. If stored below 32°F, let plastic components reach room temperature before handling. Leave the plastic covers on the connections until piping is attached.
Check in this order
- Move the crate to a solid, level surface with room for the ramp at the piping end.
- Secure the ramp to the pallet notch as the uncrating label shows.
- Remove the 16 screws and lag bolts from the 8 shipping brackets.
- Roll the boiler down the ramp onto a solid, level floor, pushing only at the jacket corners or water manifolds.
- Keep the plastic covers on the supply, return, vent and air adapters until piping is attached.
Applies to: All SVF 1500-3000 models
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: SVF 1500-3000 Series 1 boiler manual, p. 10. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.