What is going on
Piping must be done correctly or the boiler and building can be damaged. Steam supply goes on the same end as the controls; the return can connect at either end. Steam pipe sizing is in Table 7 on this page, but the column layout in the text is garbled, so confirm sizes against the printed table before cutting pipe. Keep at least 24 in. from the waterline to the bottom of the header.
Check in this order
- Install the boiler jacket before connecting the return piping; supply piping can go on before or after the jacket.
- Connect the controls only after all piping is connected.
- Size riser, header and equalizer from Table 7 for the specific model.
- Keep the header at least 24 in. minimum from the waterline to the bottom of the header.
- Use an offset header where needed so the header does not bend at the section tappings (Figure 21).
Applies to: EG/PEG steam boilers
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: EG/PEG Series 7 boiler manual, p. 24. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.