Sizing a shared combustion air duct
What is going on
Multiple boilers can share a combustion air manifold. Only air piping may be combined, never vent piping.
Check in this order
- Provide minimum clearance to adjacent vents and grade/snow line per the figure.
- Size the duct at 1 sq in of free area per 2,000 Btuh of total input, adjusted for louver restriction.
- Quick check total MBH input divided by 2 gives minimum duct area in sq in. Example: 3 x EVG 299 = 897 MBH, so 448.5 sq in.
- If a combustion air damper is used, wire the boilers so they cannot fire until the damper has opened.
Applies to: Manifolded combustion air option
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain Evergreen Series 2 advanced manual, p. 5-6. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.