Weil-McLain · Boiler troubleshooting

Sidewall wall penetration and metal cover plates

Ultra Series 4

What is going on

The cover plates and thimble set the outer stop for the vent elbow. The plate hole sizes are not readable in the extracted text, so check them against the plate supplied with the boiler.

Check in this order

  1. Cut a rough opening large enough to clear the metal thimble.
  2. Install a galvanized metal thimble (supplied by installer) in the vent pipe hole.
  3. Use cover plates with an outer plate that has a stop so the vent elbow cannot be pushed inward.
  4. Match the cover plate hole to the vent pipe size.
  5. For AL29-4C vent pipe, make the hole large enough to clear the pipe but too small for the elbow to pass through.
  6. Follow local codes for isolating vent pipe where it passes through floors or walls.

Applies to: Ultra direct exhaust sidewall termination

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Ultra Series 4 boiler manual, p. 88. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.