What is going on

Clearances for the vent and air terminations on a sidewall. The air inlet must end in a down-turned elbow and the vent in an elbow pointed away from the air inlet.

Check in this order

  1. Keep the vent at least 6 ft from adjacent walls and 5 ft below any roof overhang.
  2. Keep the vent at least 7 ft above any public walkway and at least 3 ft above any forced air intake within 10 ft.
  3. Keep the vent 12 in below or to the side of any door, window or gravity inlet for appliances up to 150,000 BTU/hr. For appliances over 150,000 BTU/hr, use 48 in.
  4. Keep the vent at least 4 ft horizontally from any electric meter, gas meter, regulator or relief valve. Do not terminate above or below these within 4 ft horizontally.
  5. Set the air termination coupling at least 12 in below the vent termination and at least 12 in above grade or snow line.
  6. Keep at least 12 in between the vent pipe and an adjacent air inlet elbow (US installations). Keep both terminations at the same height on multi-boiler installs.
  7. Keep exposed vent pipe short. Limit exterior length so condensate cannot freeze and block the vent.
  8. Install braces no more than 24 in apart. Vent and air pipes may rise to 4 ft with no enclosure; beyond 4 ft use an insulated enclosure. In extremely cold climates use an insulated chase that allows inspection.
  9. Do not terminate above a door or window, under a deck, or in building corners, window wells, alcoves or other recessed areas.
  10. Do not connect any other appliance to the vent pipe or connect multiple boilers to one vent pipe.

Applies to: Ultra boilers using separate-pipe sidewall terminations

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Ultra Series 4 boiler manual, p. 20-22. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.