Weil-McLain · Boiler troubleshooting

Sidewall direct vent: build the termination assembly

SVF Series 1

What is going on

Assemble the sidewall terminations so the vent and air pipes cannot be pushed inward.

Check in this order

  1. Cut the air pipe hole sized to the vent/air pipe maker's instructions.
  2. For combustible walls, cut the vent hole at least 3/8 in larger than the vent pipe diameter, or larger if the vent maker specifies.
  3. For noncombustible walls, size the opening per the vent maker's instructions.
  4. Install a corrosion-resistant metal thimble in the vent hole and follow local isolation codes.
  5. Fit corrosion-resistant stop plates (get them only from the vent pipe maker). Hole size must be just larger than the pipe diameter.
  6. Insert the last lengths of vent and air pipe from outside until the female shoulders rest on the stop plates.
  7. Secure external vent and air pipe runs up to 4 ft each with braces spaced no more than 24 in apart. Runs over 4 ft each need an insulated enclosure to prevent condensate freezing.
  8. Attach the exterior piping and the outward-facing vent elbow and down-turned air elbow.
  9. Install a bird screen in the open end of both termination elbows.
  10. Seal all exterior openings with exterior caulk.

Applies to: SVF 1500-3000 sidewall direct vent (Category IV)

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF Series 1 boiler manual, p. 42. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.