What is going on

Gas-tight seal at the flue collector hood and rear base is required. A leak lets flue gas and carbon monoxide spill into the room.

Check in this order

  1. Set the flue collector hood on the boiler as shown in Figure 6 (factory installed on PEG).
  2. Use the boiler cement supplied to make a gas-tight seal at the hood.
  3. For EG-30 through EG-75, fasten the rear base panels (2 pieces, 7 5/16 in. high) to the section assembly channel.
  4. Seal along the top of the insulation panels with boiler cement.

Applies to: EG/PEG Series 7, all sizes

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG/PEG Series 7 boiler manual, p. 16. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.