Approved room air venting uses 2 in or 3 in Schedule 40 PVC/CPVC or ABS, or 4 in B-vent pipe. Flexible venting (PP flex or Ubbink) is only approved for vertical non-direct vent room air installations; follow the flex vent manual. Do not install with venting in different pressure planes, as this can cause poor performance. Termination options include snorkel, side wall elbow or tee, upside-down U vertical, and vertical tee.

Likely causes

  • Venting in different pressure planes causes poor boiler performance

Check in this order

  1. Select the termination configuration that suits the building (snorkel, side wall, upside-down U vertical, or vertical tee).
  2. Use 2 in or 3 in Schedule 40 PVC/CPVC or ABS, or 4 in B-vent, as the approved pipe.
  3. Slope the horizontal exhaust 1/4 in per foot back toward the boiler.
  4. Use Ubbink or PP flex only for vertical non-direct vent room air runs, and follow the flex vent manual.
  5. Do not mix venting that runs in different pressure planes.

Applies to: Room air venting

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Rinnai I-Series Plus IP060160C installation manual, p. 45. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.