A flow switch or combustion air damper (CAD) end switch can be wired as a proof-of-closure interlock. Doing so requires removing the factory jumper on connector J18. No control settings are needed for a flow switch. For a CAD interlock, the control should be set up so the damper opens whenever the boiler is called to fire.

Check in this order

  1. Remove the jumper on connector J18 before wiring the external device.
  2. Wire the flow switch or CAD end switch to J18 as shown in the wiring diagram (Figure 76, page 78).
  3. For a CAD interlock, assign INPUT 3 as an AUX PUMP/OUTPUT function.
  4. Set the AUX PUMP/OUTPUT operating mode to local or System Damper so the damper runs on every call to fire.
  5. Wire the CAD motor to OUTPUT 3 (120VAC). If the damper motor needs another voltage or more current than the output allows, use an isolation relay.
  6. On multi-boiler installs, wire all proof-of-closure inputs in series with the end point devices and each boiler's closure switch input.
  7. Use only isolated dry contacts, because the J18 circuit carries 5 VDC.

Applies to: ECO Tec Series 3 80/110/150/199 (Combi and Heating Only)

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 72. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.