Size and space the roof holes before setting the terminations. Vent holes need extra clearance around the pipe.

Check in this order

  1. Cut the air pipe hole as close as you like to the air pipe outside diameter.
  2. Cut the vent pipe hole at least 0.4 in larger than the vent pipe: 2-3/4 in hole for 2 in pipe, 4 in hole for 3 in pipe, 5 in hole for 4 in pipe.
  3. Set a galvanized metal thimble in the vent pipe hole.
  4. Space the air and vent holes to the minimum spacing shown in Figure 23.
  5. Follow local code for isolating vent pipe through floors, ceilings and roofs.
  6. Install flashing and sealing boots sized for the vent pipe and the air pipe.

Applies to: Vertical vent/air terminations through roof

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Ultra Series 4 boiler manual, p. 24. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.