Piping multiple boilers to Easy-Fit manifolds

Evergreen Series 2

What is going on

Connect the boilers to the main header through Easy-Fit manifolds, with manifold layout and flow direction set per the piping figures.

Check in this order

  1. Size the system piping for the flow and install tees on the main for the manifolds.
  2. Connect the manifold to the main as close as practical to the midpoint of the boilers, within 8 pipe diameters.
  3. Use tees for 4 or fewer boilers. Use tees or crosses for 5 or more boilers.
  4. Put the return manifold on the return side of the main and the supply manifold on the supply side.
  5. Reverse the short and long ends of the manifolds to alternate supply and return spacing.
  6. Pipe the first boiler off the return manifold to the furthest connection on the supply manifold from the main header.
  7. Install an isolation valve on the supply and return of each boiler.
  8. Install the main air eliminator and primary circulator on the supply piping, and the expansion tank on the suction side of the system circulator.
  9. Strap system supply and return sensors at least 6 pipe diameters (no more than 3 feet) from the boiler tees.

Applies to: Multiple Evergreen boilers using Easy-Fit manifolds

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Evergreen Series 2 advanced manual, p. 6-7. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.