Weil-McLain · Boiler troubleshooting
Multiple boiler gas header and manual shutoff
What is going on
Gas header requirements when several boilers share a supply line.
Check in this order
- Build the gas header from the manifold sizing tables and the National Fuel Gas Code.
- Install a manual shutoff gas valve and ground joint union for each boiler.
- Use a 3/4-inch NPT riser from the header to the boiler for most jobs.
- Confirm that the minimum pressure at the boiler is at least 5 inches water column with all connected appliances firing.
- If the gas line enters the top of the boiler, the internal gas piping forms the drip leg.
Applies to: Ultra manifolded gas supply
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain Ultra Series 4 boiler manual, p. 93. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.