Control box, transformer and relay mounting for EG and PEG steam boilers with probe-type low water cut-off. Reference is Figure 42 and the wiring diagram on page 53.

Check in this order

  1. Turn off electrical power and the external gas supply valve before working on the boiler.
  2. Attach the junction box inside the left jacket panel with #8-32 x 1/2 inch machine screws (provided).
  3. Install the transformer with the plug-in relay receptacle and relay.
  4. Wire operating and limit circuits using 18 gauge or heavier wire.
  5. Bring supply wiring to the boiler using 14 gauge or heavier wire.

Applies to: EG and PEG steam boilers with probe-type low water cut-off

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG / PEG Series 7 Boiler Manual, p. 52. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.