Massachusetts sidewall-vented installation requirements

ECO Tec Series 3

What is going on

Required when a sidewall horizontally vented gas boiler is installed in a dwelling used for residential purposes and the vent termination is less than 7 ft above grade. Licensed plumber or gas fitter must install it.

Check in this order

  1. Confirm a hard-wired carbon monoxide detector with alarm and battery backup is installed on the floor level where the boiler is installed.
  2. Confirm a battery-operated or hard-wired CO detector with alarm is installed on each additional level served.
  3. If the boiler is in a crawl space or attic, the detector may go on the next adjacent floor level.
  4. If the detector requirements cannot be met at completion, a battery-operated CO detector with alarm must be installed and the owner has 30 days to complete the hard-wired installation.
  5. Use CO detectors that meet NFPA 720 and are ANSI/UL 2034 listed and IAS certified.
  6. Install a metal or plastic sign on the building exterior at least 8 ft above grade, in line with the vent terminal, with lettering at least 1/2 in. high reading "GAS VENT DIRECTLY BELOW - KEEP CLEAR OF ALL OBSTRUCTIONS".
  7. Leave a copy of all installation and venting instructions and parts lists with the appliance.

Applies to: ECO Tec Series 3 sidewall vent in Massachusetts

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec series 3 boiler manual, p. 29. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.