What is going on

Vent and air cap plates use a template and are fastened with screws and anchors. Plates are marked for the exhaust and intake openings.

Check in this order

  1. Set the paper template on the outside wall and level it. Mark the four mounting holes and the vent and air openings.
  2. Make sure the template is level so the vent and air pipes sit side by side.
  3. Cut the holes using a small centering bit first, then drill the large openings from both sides. A rectangular cutout may be used instead of two holes.
  4. Drill the screw holes and fasten the outside plate.
  5. Cut the vent pipe so it fully enters the termination socket, and cut the air pipe so it butts against the interior stops.
  6. Slide the pipes through the openings and fit the inside plate, sloping pipes down toward the boiler at 1/4 in per foot.
  7. Remove the pipes, drill the four mounting holes, and fasten the inside plate.
  8. Test-fit the termination on the vent pipe.
  9. Apply silicone RTV sealant inside the vent termination and slide it onto the vent pipe. Rotate slightly to spread the sealant.
  10. Secure the termination with four #10 x 1/2 in sheet metal screws and lock washers.

Applies to: W-M vent/air plate and cap, sidewall direct vent

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 37-38. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.