Install the wall-mount bracket
What is going on
Bracket must be fastened only to wall studs and must be level before the boiler is hung.
Check in this order
- Locate the studs. They must be on 16-inch centers; for other spacing provide a secure, solid mounting surface.
- Hold the wall-mount bracket on the wall, level it, and center the slots over the studs.
- Trace the screw slot outlines with a pencil.
- Remove the bracket and drill 1/4 inch diameter holes, 3 inches deep, centered on the outlines (use required clearance holes for metal studs).
- Position the bracket and insert and loosely tighten the two lag screws (3/8 x 3 inch) or toggle bolts for metal studs.
- Level the bracket, then tighten the lag screws. On drywall or plaster lath, do not tighten so much the bracket digs in.
- Install additional screws in the center holes for full support.
Applies to: Wall mount installations
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: ECO Tec Series 3 boiler manual, p. 14. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.