What is going on

Bracket must be fastened only to wall studs and must be level before the boiler is hung.

Check in this order

  1. Locate the studs. They must be on 16-inch centers; for other spacing provide a secure, solid mounting surface.
  2. Hold the wall-mount bracket on the wall, level it, and center the slots over the studs.
  3. Trace the screw slot outlines with a pencil.
  4. Remove the bracket and drill 1/4 inch diameter holes, 3 inches deep, centered on the outlines (use required clearance holes for metal studs).
  5. Position the bracket and insert and loosely tighten the two lag screws (3/8 x 3 inch) or toggle bolts for metal studs.
  6. Level the bracket, then tighten the lag screws. On drywall or plaster lath, do not tighten so much the bracket digs in.
  7. Install additional screws in the center holes for full support.

Applies to: Wall mount installations

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 14. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.