Weil-McLain · Boiler troubleshooting

Install sidewall direct vent with separate pipes

ECO Tec Series 3

What is going on

Vent and air pipes run through two separate sidewall openings. The layout must meet the termination clearances.

Check in this order

  1. Confirm the boiler location lets vent and air pipe run to the chosen sidewall spot.
  2. Check the sidewall location against the termination clearance figure before cutting.
  3. Use only listed vent materials and adapters. Stay within the maximum vent and air lengths.
  4. Cut the penetrations and install the sidewall plates as described.
  5. Slope horizontal piping down toward the boiler at least 1/4 in per foot.
  6. Support pipe every 5 ft on horizontal and vertical runs, with a hanger within 6 in of any upturn.
  7. Fit the air pipe with a down-turned elbow and the vent pipe with an elbow pointed away from the air inlet.
  8. Keep the air coupling at least 12 in below the vent termination and at least 12 in above grade or snow line.
  9. If an external pipe is longer than 4 ft, enclose it in insulation so condensate cannot freeze in it.
  10. Brace external pipes no more than 24 in apart and keep all clearances.

Applies to: Sidewall direct vent, separate pipes

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 33-34. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.