Install sidewall concentric vent termination

ECO Tec Series 3

What is going on

The concentric kit is bought separately and must be assembled and mounted before the piping runs to the boiler.

Check in this order

  1. Read the vent and air piping instructions and confirm the wall location meets termination clearances.
  2. Assemble the concentric termination and mount it before running piping from the boiler.
  3. Cut the wall opening. A thimble with a 4-1/2 in hole is preferred. If cutting without a thimble, do not exceed 4-3/4 in.
  4. Make sure the wall opening gives a solid stop for the rain cap ribs.
  5. Secure the termination so the rain cap butts against the outer wall or thimble plate.
  6. Support the termination so it cannot slip or move. Keep clamps off the pipe to prevent cracking.
  7. Run vent and air piping from the boiler to the termination. Do not let the piping weight rest on boiler fittings.
  8. Place a bird screen on the inner pipe end and cement the rain cap once the assembly is set.

Applies to: Sidewall concentric direct vent

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 35-36. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.