Inserting PVC or ABS vent or air pipe into boiler connector
What is going on
Seal comes from the internal gasket, so the clamp only holds the pipe in place.
Likely causes
- Rough or unchamfered pipe end damages the adapter gasket
- Pipe not inserted to the mark
- Clamp overtightened or adapter bent
Check in this order
- Clean and chamfer the insertion end of the pipe and deburr its inside.
- Check the adapter for obstructions or foreign objects.
- Loosen the adapter clamp screw.
- Measure 3-1/2 inches from the pipe end and mark it.
- Apply a small amount of silicone grease to the pipe end.
- Insert the pipe into the adapter and slide it down to the 3-1/2 inch mark.
- Tighten the clamp securely but do not overtighten.
- Do not bend the adapter or pipe or force the insertion.
Applies to: Boiler vent connector and air pipe connector
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Ultra Series 4 boiler manual, p. 82. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.