Hydrostatic pressure test procedure
What is going on
Pressure test the boiler before connecting permanent piping. Use Figure 2 for the connection layout.
Check in this order
- Remove the supply line tees and 3/4 in elbow from the accessory bag and pipe them to the supply connection. Use pipe dope sparingly.
- Temporarily plug the 3/4 in relief valve tapping in the street elbow with a 3/4 in NPT plug.
- Connect a hose from the fresh water supply to the boiler drain valve. Make sure it can also drain the boiler after the test.
- Install a nipple and shutoff valve on the supply tee to bleed air during fill (not included with boiler).
- Install a shutoff valve on the return connection (not included with boiler).
- Pipe street elbows on top of the shutoff valves and place catch buckets below if you want to avoid water on the boiler.
- Open the shutoff valves, then slowly open the drain valve and fresh water supply to fill. Close the drain when water reaches the shutoff valves.
- Close the shutoff valves, then slowly reopen the drain until the gauge reads 45 to 55 psig.
- Hold for 10 minutes and confirm the gauge pressure stays constant. Check for leaks and repair any found.
- Disconnect the fill hose, drain the boiler through the drain valve, and remove the hose.
- Remove the nipples and valves unless they stay in the system piping.
- Remove the plug from the relief valve street elbow and install the relief valve per page 9.
Applies to: Ultra Series 4 boilers
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Weil-McLain Series 4 gas-fired water boiler manual, p. 8. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.