What is going on

The SVF must be vented and given combustion and ventilation air only with the piping and methods in this manual. Category IV boilers must not be common vented, and each boiler needs its own vent. Inspect the finished vent and air piping for airtightness and correct size.

Check in this order

  1. Use only the vent and air methods in this manual.
  2. Do not common vent the boiler with any other appliance.
  3. Inspect the finished vent and air piping for airtight joints and code compliance.
  4. Confirm all air openings are sized correctly, unobstructed and free of airborne contaminants.
  5. Do not insulate nonmetallic vent pipe.
  6. Provide combustion air per NFPA 54 section Air for Combustion and Ventilation, or CAN/CSA B149.1 sections 8.2 to 8.4, or local code.
  7. Choose Method 1 (direct exhaust, air from the boiler room, sidewall or vertical termination) or Method 2 (direct vent, air piped from outside, sidewall or vertical termination).

Applies to: All SVF 1500, 2000, 2500 and 3000 installations

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: SVF Series 1 Boiler Manual, p. 25. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.