Floor foundation and flooring requirements

ECO Tec Series 3

What is going on

Requirements for floor-standing installations using the pedestal kit.

Check in this order

  1. Never install the boiler on carpeting, even when a foundation is used.
  2. Use a solid foundation pad at least 2 inches above the floor if the floor can flood, is dirt, sand, gravel or loose material, or the mounting area is badly uneven or sloped.
  3. Minimum foundation size for ECO Tec is 20 inches wide by 20 inches deep.
  4. Foundation may be wood, brick or concrete, at least 2 inches thick.
  5. If flooding is possible, raise the boiler high enough that water cannot reach it.

Applies to: Floor-standing installations with pedestal kit

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: ECO Tec Series 3 boiler manual, p. 13. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.