Weil-McLain · Boiler troubleshooting

Example D high mass boiler with isolation heat exchanger

Evergreen Series 2

What is going on

Condensing boilers run during low-load periods such as spring and fall. A high-mass boiler is added for high-load periods. The control sequences the high-mass boiler in when it is needed, through the additional heat demand input.

Check in this order

  1. Pipe the isolation heat exchanger and high-mass boiler as shown in Figure 15.
  2. Install unions where recommended, drain valves at 3/4 inch NPT or larger, and the boiler T&P gauge.
  3. Provide a strainer on each boiler return line where recommended.
  4. Place immersion sensors on the supply and return at least 6 pipe diameters, and no more than 3 feet, from the boiler connection tees.
  5. Confirm the control sequences the high-mass boiler when needed.

Applies to: Example D multi-boiler with isolation heat exchanger and high-mass boiler

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Series 2 Condensing Gas Boiler Advanced Manual, p. 31. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.