Weil-McLain · Boiler troubleshooting

Example D control setup and circulator supply

Evergreen Series 2

What is going on

The required settings are in Table 7, which is not on these pages. The ODT setpoint and the activate contact below setpoint must match the design conditions of the system. Unlike Example C, the boiler circulator must be supplied by the installer.

Check in this order

  1. Make settings with the WIZARD or with the manual menu steps elsewhere in the manual.
  2. Set the ODT setpoint to the system design outdoor temperature.
  3. Set the activate contact below setpoint to the system design condition.
  4. Supply the boiler circulator and follow all piping instructions for the boiler and system.
  5. Check FLA, locked rotor and inrush for the boiler and system circulators against the relay limits.

Applies to: Example D multi-boiler with high-mass boiler

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Series 2 Condensing Gas Boiler Advanced Manual, p. 32. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.