Weil-McLain · Boiler troubleshooting

Electrical supply and line voltage

Ultra Series 4

What is going on

Line voltage wiring requirements for the U-Control boiler.

Check in this order

  1. Turn off power at the service entrance panel before any connection.
  2. Provide a fused disconnect or service switch, 15 A rated recommended, as code requires.
  3. Connect at least a 15 A, 120 VAC supply to the boiler line voltage terminal strip.
  4. Wiring must be N.E.C. Class 1.
  5. If the factory wiring must be replaced, use 105 °C wire or equivalent.
  6. Ground the boiler as required by NEC ANSI/NFPA 70 and local codes.
  7. In Canada, follow CSA C22.1 Canadian Electrical Code Part 1 and local codes.

Applies to: Ultra U-Control line voltage

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Ultra Series 4 boiler manual, p. 94. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.