Weil-McLain · Boiler troubleshooting

Electrical installation requirements before wiring

Evergreen Pro Series 2

What is going on

Basic rules from the manual that must be met before making any electrical connection.

Check in this order

  1. Turn off the electrical supply at the service entrance panel before making any connection.
  2. Do not use a 24 V transformer to power any external device that is not listed in the manual.
  3. Use NEC Class 1 wiring. If the original boiler wire must be replaced, use 105 °C wire or equivalent.
  4. Electrically ground the boiler as the code requires, and bond it to ground where the authority having jurisdiction requires it.
  5. Label every wire to make sure connections are correct.
  6. Do not jumper or bypass any device except for momentary testing.
  7. Seal all electrical entrances with a sealed strain relief or duct seal putty or silicone so the boiler does not draw room air.

Applies to: All Series 2 boilers

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Weil-McLain Series 2 advanced manual 550-100-581/0325, p. 45-46. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.