What is going on
The termination needs the boiler kit plates plus installer-supplied parts; do not leave exposed vent pipe longer than shown.
Likely causes
- Exposed vent pipe too long, condensate freezes and blocks the vent
- Outer plate with no stop, so the elbow can be pushed inward
Check in this order
- Gather installer-supplied vent piping, cover plates, galvanized thimble, vent termination elbow and bird screen.
- Trim the supplied metal plates for cover plates only when the hole size matches the vent diameter.
- Insert the piping from the boiler vent connection, then attach the exterior termination piping.
- Install the vent termination using one of the two configurations in Figure 98.
- Seal exterior openings with exterior caulk.
- Do not extend exposed vent pipe outside the building more than the manual shows.
Applies to: Ultra direct exhaust sidewall termination
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Ultra Series 4 boiler manual, p. 88. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.