With a counterflow system, the boiler steam supply must tie into the top of the counterflow header. Figure 22 on the next page shows the arrangement.

Check in this order

  1. Connect the boiler steam supply into the top of the counterflow system header.
  2. Check the connection against Figure 22 before final connection.

Applies to: EG/PEG steam boilers on counterflow systems

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG/PEG Series 7 boiler manual, p. 24. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.