Connect gas supply piping to boiler
What is going on
Gas connection is ½ in. NPT male on top of the boiler. Installer supplies the shut-off valve and fittings.
Check in this order
- Use a pipe wrench on the gas line at the top of the boiler while tightening the gas line assembly to the boiler connection.
- Use two wrenches when tightening gas piping at the boiler so the boiler gas connection does not turn.
- Install steel pipe fittings per Figure 74 with a manual gas shut-off valve, union, and drip leg (tee, 4 in. nipple, cap).
- Apply pipe dope sparingly to male threads only, and use pipe dope compatible with propane.
- In Canada, identify the manual gas shut-off valve.
- Support gas piping with hangers, not by the boiler or its accessories.
- Purge all air from the gas supply piping.
Applies to: ECO Tec Series 3 all models
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: ECO Tec series 3 condensing gas boiler boiler manual, p. 64. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.