Commissioning check-out highlights before handover

Ultra Series 4

What is going on

Key verifications from the startup checklist. Complete full checklist and certificate on page 140.

Check in this order

  1. Confirm the U-Control is set for the correct boiler model and installation date/contact entered.
  2. Confirm boiler and heat distribution units are filled, water chemistry is verified, and inhibitor added.
  3. Purge air from system and from gas piping; check gas piping for leaks; confirm condensate trap is primed.
  4. Confirm propane orifice and propane conversion label if firing propane.
  5. Check thermostat circuit wiring for stray voltages.
  6. Verify burner flame and combustion per page 40.
  7. Verify space heating and DHW control operation; test any field-installed limits or low water cutoff for proper lockout.
  8. Cycle the boiler with the thermostat at highest and lowest settings and confirm startup and shutdown.
  9. Measure natural gas input and check incoming gas pressure (see gas pressure setting).
  10. Observe several operating cycles, set room thermostat, and fill out the Installation and Service Certificate.

Applies to: Ultra Series 4 startup

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ultra Series 4 gas-fired water boiler manual, p. 42. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.