What is going on

Confirm the install follows the local codes, the National Fuel Gas Code (NFPA 54 / ANSI Z223.1), the NEC (NFPA 70) and, in Canada, CAN/CSA B149.1 or B149.2. Massachusetts installs need a licensed plumber and a reduced pressure backflow preventer if antifreeze is used. Check the site for nearby water, vent, gas and electrical connections, and clear out combustibles, flammable liquids and contaminants. Replacing an old boiler means fixing system faults first: leaks causing oxygen corrosion, a wrongly sized expansion tank, or no antifreeze in a freeze-prone system.

Check in this order

  1. Confirm local, state, provincial and national code requirements apply to the install.
  2. Confirm the boiler is protected from dripping or spraying water and rain during operation and service.
  3. Clear the area of combustibles, gasoline and other flammable liquids.
  4. On a replacement, correct system leaks, expansion tank sizing and freeze protection before setting the new boiler.

Applies to: EG and PEG Series 7 boilers, site preparation

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG / PEG Series 7 Boiler Manual, p. 8. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.