Chimney and vent termination requirements

EGPEG

What is going on

Vent must follow NFPA 54 and local codes. Chimneys and non-Type B vents must extend at least 3 ft above the roof penetration and 2 ft above any building within 10 ft. Type B vents with a listed cap may end as shown in Figure 3 if at least 8 ft from a vertical wall. Otherwise Type B vents must end at least 2 ft above the roof and 2 ft above any building within 10 ft. Keep vent and air intake areas clear of snow.

Likely causes

  • Cold masonry chimney condensation damaging the masonry
  • Vent termination too close to a wall or roof obstruction

Check in this order

  1. Check the chimney is lined. A lined chimney is preferred and required by some codes.
  2. Use a corrosion-resistant liner such as AL29-4C single-wall stainless or a correctly sized B-vent in cold masonry chimneys.
  3. Provide a drain trap in cold masonry chimneys to remove condensate.
  4. For shared chimneys, size the common vent to equal the largest appliance vent outlet plus 50 percent of each additional appliance outlet.
  5. Confirm the vent height and clearance above grade or snow line.

Applies to: EG and PEG venting

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: EG / PEG Series 7 Boiler Manual, p. 11 (see Ratings table p. 89 for minimum vent sizes). Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.