Weil-McLain · Boiler troubleshooting
Check control module fuses
What is going on
Check both fuses before replacing the control module or major components such as the blower.
Likely causes
- Blown low voltage fuse
- Blown line voltage fuse
Check in this order
- Turn off power to the boiler at the external line switch.
- Remove the jacket door and top panel. Swing the control panel forward to reach the U-Control module.
- Remove and inspect both fuses.
- Replace the low voltage fuse with a 3 A fast-blow (Littelfuse 257003) if needed.
- Replace the line voltage fuse with a 12 A slow-blow (Littelfuse 326012P) if needed.
- Never jumper a fuse or fit a different rating.
- Refit the top panel and jacket door, restore power, and verify operation.
Applies to: Ultra 80, 105, 155, 230, 299, 399
More boiler guides
- 0-10 VDC output for controlling another heat source (P16 pins 1 and 2)
- 0-10 VDC remote modulation input
- 0-10VDC output for lead/lag and variable speed pump
- 120 VAC power supply connection to terminal strip T1
- A sensor is missing from the list at power-up
- Access and clean exchanger, Ultra-155, -230, -299 and -399
Related
Weil-McLain error codes · Weil-McLain parts · Weil-McLain tips · Calculators and reference tables
Take it to the job
All guides, error codes and tips work offline in the HVACopedia app.
Source: Ultra Series 4 gas-fired water boiler manual, p. 116. Written in our own words; check the manual for your exact model.
For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.