What is going on

Connect the heating circuit to the two bottom connections of the boiler. Purge the system first, because debris and air in the lines will damage the boiler. Piping must follow state and local plumbing codes.

Check in this order

  1. Connect the heating return line to the heating return connection on the bottom of the boiler.
  2. Connect the heating supply line to the heating supply connection on the bottom of the boiler.
  3. Purge the heating system of all debris and air before connecting the boiler.
  4. Install an air separator on the central heating supply side.
  5. Insulate system piping where freezing is a possible concern.
  6. Do not connect the boiler directly to a system that uses polybutylene or other oxygen-permeable piping.
  7. If oxygen-permeable tubing is used, install a plate heat exchanger to isolate the tubing from the boiler.
  8. Use hydraulic separation with primary/secondary piping when connecting the water supply.

Applies to: Heating return and supply connections

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Rinnai I-Series Plus IP060160C installation and operation manual, p. 57-58. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.