What is going on

Dry-fit the full run first, then cement each joint so it seals and does not leave excess cement inside.

Check in this order

  1. Work from the boiler toward the termination and do not exceed the maximum lengths for air or vent.
  2. Install pipe reducers where needed at the boiler and at the termination assembly.
  3. Cut pipe to length, deburr inside and outside of each end, and chamfer the outside of each end.
  4. Clean all pipe ends and fittings, then dry them.
  5. Dry-assemble the full vent or air run before cementing any joint.
  6. For each joint, apply primer to both the pipe end and fitting socket while it is still wet.
  7. While primer is damp, apply approved cement evenly to both surfaces, then apply a second coat.
  8. Insert the pipe fully with the cement still wet, twisting about 1/4 turn.
  9. Wipe excess cement and confirm a smooth bead shows around the whole joint.
  10. Install pipe supports as shown in Figure 76 on page 70.

Applies to: Ultra vent and air piping (PVC/ABS)

More boiler guides

Take it to the job

All guides, error codes and tips work offline in the HVACopedia app.

Open the app

Source: Ultra Series 4 boiler manual, p. 71. Written in our own words; check the manual for your exact model.

For licensed technicians. Gas, electrical and refrigerant work must be done by a qualified, licensed person. Shut off power and gas before servicing, never bypass a safety control, and follow the manufacturer’s manual for the exact model; it and local codes always take priority. HVACopedia is not affiliated with any manufacturer; brand and model names only identify the equipment.